Build Target Bottleneck Detection

Databricks interview questions · Medium · Coding round · reported 1× · 6 tests

You are given a DAG of build targets. Each target has a duration and may depend on other targets. With unlimited workers, the total build time is determined by the critical path: the longest dependency chain leading into the requested target.